Week 25 · 2026
Jun 15 – Jun 21, 2026 · gathered Jul 15, 2026
- 0
- PRs merged
- 0
- Closed
- 0
- Opened
- 0
- Releases
- 2
- Repos
- 12
- Commits
- 0
- Comments
Highlights
A heads-down building week with both flagship deliverables advancing in parallel.
Most of the momentum was on contracts-library (our OpenZeppelin-style library of audit-ready Cardano smart contracts), where we shipped:
- Our first complete contract end to end: Linear Vesting, containing an on-chain validator, off-chain code and a written specification
- The Aiken project setup,
- CIP-113 native-token vault groundwork
- CI/CodeQL.
Meanwhile cardano-init, the "spin up a Cardano project in minutes" setup CLI, gained:
- Its
doctorcommand: a one-shot check that a developer's environment has everything it needs - Hardened smoke-test CI.
Two of the initiative's biggest deliverables are now being built at the same time, week after week.
Activity
Merged PRs, issues, and releases grouped by deliverable — the evidence behind the narrative above.
D3 Setup CLI/TUI
In progress3 commits · input-output-hk/cardano-init
D5 Contracts Library
In progress9 commits · input-output-hk/contracts-library